Ask Question
5 May, 02:19

36

Select the correct answer.

What is the purpose of the sprint retrospective activity in the Scrum process?

A. to organize meetings to discuss problems

B. to evaluate the time required to accomplished the work of an entire sprint

C. to review the demonstration of the product backlog items and update them accordingly

D.

to recruit people with cross-functional skills for the sprint

E.

to reviewing the complete Scrum process to identify defects and plan for future development

Reset

+4
Answers (2)
  1. 5 May, 03:20
    0
    I believe it's d hope it's right
  2. 5 May, 06:03
    0
    Answer: E

    Explanation:As described in the Scrum Guide, the Sprint Retrospective is an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “36 Select the correct answer. What is the purpose of the sprint retrospective activity in the Scrum process? A. to organize meetings to ...” in 📘 Arts if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers