A summary of tanner company's flexible budget of manufacturing costs follows: 10,000 units direct materials $30,000 direct labor 35,000 variable factory overhead 15,000 fixed factory overhead 16,000 total $96,000 what would the flexible budget of manufacturing costs be at a production volume of 12,000 units?

a. $109,000

b. $80,000

c. $112,000

d. $115,200

+3
Answers (1)
  1. Yesterday, 16:43
    0
    The answer is c. $112,000. The quickest way to arrive at this answer is to notice that 12,000 is a 20% increase over 10,000. Fixed costs remain the same, so the flexible budge for 12,000 units is (96,000 - 16,000) *.2 + 96,000 = 112,000. A better way, or at least more generalizable, way to approach the problem is to calculate and sum the per unit cost for each variable factor, multiply that by the number of units, and then add the fixed costs. So: [ (material/unit + labor/unit + variable overhead/unit) x units] + fixed overhead = cost
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A summary of tanner company's flexible budget of manufacturing costs follows: 10,000 units direct materials $30,000 direct labor 35,000 ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers