Messersmith company is constructing a building. construction began in 2014 and the building was completed 12/31/14. messersmith made payments to the construction company of $2,000,000 on 7/1, $4,200,000 on 9/1, and $4,000,000 on 12/31. weighted-average accumulated expenditures were

+5
Answers (1)
  1. 27 January, 10:04
    0
    The answer is, "weighted-average accumulated expenditures were $2,400,000".

    we can calculate this as;

    payments made are:

    $2,000,000 on 7/1, $4,200,000 on 9/1, and $4,000,000 on 12/31

    So,

    ($2,000,000 * 6/12) + ($4,200,000 * 4/12

    = $2,400,000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Messersmith company is constructing a building. construction began in 2014 and the building was completed 12/31/14. messersmith made ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.