Management recently instituted a new training program for upper level managers. they budgeted the cost of the new program at $1,000 per employee trained but actual costs were $1,250 per employee trained. the difference between the budgeted cost for training and the actual cost of training is called a:

+5
Answers (1)
  1. 15 March, 10:01
    0
    The difference between the actual and budgeted cost is termed the variance. In this case, that variance shows that the training program ran over budget by $250 per employee.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Management recently instituted a new training program for upper level managers. they budgeted the cost of the new program at $1,000 per ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.