Ask Question
23 September, 12:58

West company estimates that overhead costs for the next year will be $5,240,000 for indirect labor and $550,000 for factory utilities. the company uses machine hours as its overhead allocation base. if 150,000 machine hours are planned for this next year, what is the company's plantwide overhead rate? $.0259 per machine hour. $34.93 per machine hour. $38.60 per machine hour. $.2727 per machine hour. $3.67 per machine hour.

+4
Answers (2)
  1. 23 September, 14:35
    0
    We need overhead rate in total cost/machine hour, so

    total cost = 5,240,000+550,000 = 5,790,000

    total machine hours = 150,000

    Average overhead = 5,790,000 / 150,000

    =$38.60 / machine hour.
  2. 23 September, 16:26
    0
    Predetermined oH rate is

    (5,240,000+550,000) : 150,000

    =38.6 per machine hour
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “West company estimates that overhead costs for the next year will be $5,240,000 for indirect labor and $550,000 for factory utilities. the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers