An activity's normal time and cost are 8 and $100, respectively. its estimated crash time and cost are 6 and $160, respectively. what is this activity's crash cost per time unit?

+3
Answers (1)
  1. 8 August, 13:05
    0
    An activity's normal time and cost are = 8 and $100 respectively

    estimated crash time and cost are = 6 and $160 respectively

    Activity's crash cost per unit time = ?

    crash cost per unit time = cost slope and,

    cost slope = rise/run = (crash cost - normal cost) / (normal time - crash time)

    cost slope = (160 - 100) / (8 - 6) = 60 / 2 = $30

    so, crash cost per unit time is $30.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “An activity's normal time and cost are 8 and $100, respectively. its estimated crash time and cost are 6 and $160, respectively. what is ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.