Dudly drafting services uses a 45% material loading charge and a labor rate of $20 per hour. how much will be charged on a job that requires 3.5 hours of work and $40 of materials? $128 $110 $88 $133

+4
Answers (1)
  1. 14 March, 19:50
    0
    How to get material loading charge total;

    is. ℅

    _ = _ x 45

    of 100 _ = _

    40. 100 = $18

    How to get labor charge total;

    20*3.5. = $70

    How to get total for all charges;

    $70+$18

    Answer = $88
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Dudly drafting services uses a 45% material loading charge and a labor rate of $20 per hour. how much will be charged on a job that ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.