7 February, 12:14

The total completion time is 25 days. task a is planned to take seven days. task b is planned to take five days. task c is planned to take eight days. the tasks have a serial relationship. how much slack does the project have?

+4
Answers (1)
  1. 7 February, 14:40
    0
    The project currently has Positive 5 days slack.

    Times needed for task A = 7 days

    Times needed for task B = 5 days

    Times needed for task C = 8 days

    Total predicted days = 20 days

    Since the project is required to be completed in 25 days, the company has 25 days - 20 days = 5 days positive
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The total completion time is 25 days. task a is planned to take seven days. task b is planned to take five days. task c is planned to take ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.