The predetermined overhead rate for concord corporation is $5, comprised of a variable overhead rate of $3 and a fixed rate of $2. the amount of budgeted overhead costs at normal capacity of $150000 was divided by normal capacity of 30000 direct labor hours, to arrive at the predetermined overhead rate of $5. actual overhead for june was $8288 variable and $5040 fixed, and 1400 units were produced. the direct labor standard is 2 hours per unit produced. the total overhead variance is

+5
Answers (1)
  1. 30 September, 12:00
    0
    Actual overhead=8,288+5,040=13,328

    Estimated overhead

    5 * (2*1,400)

    5*2800 direct labor hours

    =14,000

    The total overhead variance

    14,000-13,328

    =672 over applied
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The predetermined overhead rate for concord corporation is $5, comprised of a variable overhead rate of $3 and a fixed rate of $2. the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers