Refer to the table below. what is the cumulative budgeted cost at the end of week 6? amounts are in thousands of dollars.

+5
Answers (1)
  1. 28 November, 19:30
    0
    The cumulative budgeted cost at the end of week 6 is $100,000. The answer in this question whose are amounts are in thousand of dollars is $100,000. So, the cumulative budgeted cost at the end of the week 6 is $100,000. Cumulative budgeted cost or acronym of CBC is the amount that is budgeted in order to accomplish the work that was scheduled.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Refer to the table below. what is the cumulative budgeted cost at the end of week 6? amounts are in thousands of dollars. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.