Case company allocates $5 overhead to each unit produced. the company uses a plantwide overhead rate with machine hours as the allocation base. given the amounts below, how many machine hours does the company expect in department 2?

+1
Answers (1)
  1. 26 July, 08:07
    0
    Let Department 2 Machine hours Be x, and using the equation below.

    Find ATQ:

    5 = (440000 + 245000) / (74000 + x)

    => 370000 + 5x = 685000

    =>x = 63000

    Therefore, there are 63,000 machine hours that the company expects in Department 2.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Case company allocates $5 overhead to each unit produced. the company uses a plantwide overhead rate with machine hours as the allocation ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.