Ask Question
12 May, 08:41

A project will produce an operating cash flow of $14,600 a year for 7 years. the initial fixed asset investment in the project will be $48,900. the net aftertax salvage value is estimated at $12,000 and will be received during the last year of the project's life. what is the net present value of the project if the required rate of return is 12 percent?

+4
Answers (1)
  1. 12 May, 10:48
    0
    Answer: The net present value is the sum of the three present values. NPV = PV of initial investment + PV of 7 year annuity + PV of lump sum salvage NPV = - 48900 + 14600 x (1 - 1 / (1 + 12%) ^7) / 12% + 12000 / (1+12%) ^7 = 23,159.04
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A project will produce an operating cash flow of $14,600 a year for 7 years. the initial fixed asset investment in the project will be ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers