As the project progresses from initiation through planning and executing, and additional detail is gathered, the range of values for the project cost estimate will:

+4
Answers (1)
  1. 18 April, 20:20
    0
    The range of values for the project cost estimate will become more precise. As in, there will be a better and more clear idea of how much the project costs will be, so the estimate will be more accurate.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “As the project progresses from initiation through planning and executing, and additional detail is gathered, the range of values for the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.