The 50th repetition of a job is timed at 100 minutes. if the learning curve for this job is 90 percent, what is the estimated time for the 200th repetition of this job?

+2
Answers (1)
  1. 6 October, 08:46
    0
    It would be 81 minutes.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The 50th repetition of a job is timed at 100 minutes. if the learning curve for this job is 90 percent, what is the estimated time for the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.