The estimated variance for an activity with a most likely time (m) equal to 11 days, the optimistic time (a) equal to 6 days, and the pessimistic time (b) equal to 18 days is

+4
Answers (1)
  1. 4 December, 02:06
    0
    4 days. This has to do with business management and the idea that different types of time based on the mindset varies between how much work and activity will actually be done.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The estimated variance for an activity with a most likely time (m) equal to 11 days, the optimistic time (a) equal to 6 days, and the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.