Activity Base Data Estimated number of DLH for the year 6,250 Estimated number of MH for the year 4,375 Compute the predetermined factory overhead rate for the current year.

+1
Answers (1)
  1. 18 November, 00:37
    0
    Instructions are below.

    Explanation:

    Giving the following information:

    Estimated Direct labor hours = 6,250

    Estimated Machine hours = 4,375

    We weren't provided with the estimated manufacturing overhead for the period. But, with an example, I can guide the answer.

    To calculate the estimated manufacturing overhead rate we need to use the following formula:

    Estimated manufacturing overhead rate = total estimated overhead costs for the period / total amount of allocation base

    For example:

    Estimated overhead for the period = $275,000

    For Direct labor hours:

    Estimated manufacturing overhead rate = 275,000/6,250 = $44 per direct labor hours

    For Machine-hours:

    Estimated manufacturing overhead rate = 275,000/4,375 = $62.86 per machine hour
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Activity Base Data Estimated number of DLH for the year 6,250 Estimated number of MH for the year 4,375 Compute the predetermined factory ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.