If A, B, and C are three activities connected with SS and FF (combination) relationships with no lags, their durations are 5, 10, and 3; respectively. What is the duration of the project?

+1
Answers (1)
  1. 23 September, 15:56
    0
    10 days

    Explanation:

    The Critical Path Method is a method of managing activities in a project so as to maximize time. In the case of A, B and C activities, since they are connected with the same start-to-start and finish-to-finish, it means that the activities are linked and as such the duration of the project is 10 days since the last activity will take 10 days to finish.

    The implication between SS and FF in the activities means that they start up at the same time in the CPM and while activity A ends at 5 days, C proceeds to 10 days.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “If A, B, and C are three activities connected with SS and FF (combination) relationships with no lags, their durations are 5, 10, and 3; ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers