Tally Company uses job costing. The job cost record for Job A61 on March 1 showed a balance of $5,200. The job was completed on March 16. During March materials requisitions for this job were $2,300. Labor time records for this job in March were $4,000. Manufacturing overhead is allocated based on direct labor cost. The rate is 90% of direct labor cost. How much is the total cost of Job A61?

+2
Answers (1)
  1. 7 February, 23:16
    0
    Total cost = $15,100

    Explanation:

    Giving the following information:

    The job cost record for Job A61 on March 1 showed a balance of $5,200.

    Job A61:

    March:

    Direct materials = $2,300.

    Direct Labor = $4,000.

    Manufacturing overhead is allocated based on direct labor cost. The rate is 90% of direct labor cost.

    MOH = 4000*0.9 = $3,600

    Total cost = 5,200 + 2,300 + 4,000 + 3,600 = $15,100
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Tally Company uses job costing. The job cost record for Job A61 on March 1 showed a balance of $5,200. The job was completed on March 16. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.