Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below:
Hours
Wait time
28.0
Process time
1.0
Inspection time
0.4
Move time
3.2
Queue time
5.1
The delivery cycle time was:
A) 8.3 hours
B) 3.2 hours
C) 37.7 hours
D) 36.3 hours
+1
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours Wait ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.