White Company has two departments, Cutting and Finishing.

The company uses a job-order costing system and computes a predetermined overhead rate for each department. The Cutting Department bases its rate on machine-hours and the Finishing Department bases its rate on direct labor-hours.

At the beginning of the year, the company made the following estimates:

Department

Cutting Finishing

Direct labor-hours 7,700 43,000

Machine-hours 43,400 1,900

Total fixed manufacturing overhead cost $390,000 $496,000

Variable manufacturing overhead per machine-hour $2.00

Variable manufacturing overhead per direct labor-hour $3.75

Compute the predetermined overhead rate for each department.

+3
Answers (1)
  1. 17 October, 01:26
    0
    Cutting = $10.99 per machine hour

    Finishing = $15.28 per direct labour hours.

    Explanation:

    The question requests the predetermined overhead rate for Cutting department and Finishing department

    Step 1: What is the formula for the pre-determined overhead rate

    For the Cutting Department

    Predetermined Overhead rate = The total fixed manufacturing Overhead / Total Machine Hours + Variable Manufacturing Overhead rate per machine hour.

    = $390,000/$43,400) + $2

    = $10.99 per machine hour

    For the Finishing Department

    Predetermined Overhead rate = The total fixed manufacturing Overhead / Total Labour Hours + Variable Manufacturing Overhead rate per machine hour.

    = $496,000/43,000) + $3.75

    = $15.28 per direct labour hours.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and computes a predetermined overhead ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.