Jasper Carts manufactures custom carts for a variety of uses. The following data have been recorded for Job 651, which was recently completed. Direct materials used cost $8.200. There were 179 direct labor hours worked on this job at a direct labor wage rate of $28.00 per hour. There was 90 machine hours used pm this job. The predetermined overhead rate is $3700 per machine hour used. What is the total manufacturing cost of Job 651? $5, 012 $8, 469 $3, 330 $16, 542

+5
Answers (1)
  1. 15 March, 23:20
    0
    The correct answer is D.

    Explanation:

    Giving the following information:

    The direct materials used cost $8.200. There were 179 direct labor hours worked on this job at a direct labor wage rate of $28.00 per hour. There were 90 machine hours used pm this job. The predetermined overhead rate is $37.00 per machine hour used.

    Total cost:

    Direct material = 8,200

    Direct labor = 179*28=5,012

    MOH = 37.00*90 = 3,330

    Total = $16,542
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Jasper Carts manufactures custom carts for a variety of uses. The following data have been recorded for Job 651, which was recently ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.