Bonita Industries has a materials price standard of $2.00 per pound. 4600 pounds of materials were purchased at $2.20 a pound. The actual quantity of materials used was 4600 pounds, although the standard quantity allowed for the output was 3400 pounds. Bonita Industries's materials quantity variance is

+5
Answers (1)
  1. 1 August, 17:08
    0
    Total Materials Variance = $3320

    Explanation:

    given data

    materials price standard = $2.00 per pound

    materials purchased = 4600

    purchased at = $2.20 a pound

    actual quantity materials used = 4600 pounds

    standard quantity allowed output = 3400 pounds

    to find out

    Bonita Industries's materials quantity variance

    solution

    we get here Total Materials Variance that is express as

    Total Materials Variance = Actual Quantity * Actual Rate - Standard Quantity * Standard Rate ... 1

    put here value we get

    Total Materials Variance = 4600 * 2.20 - 3400 * 2

    Total Materials Variance = $3320
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Bonita Industries has a materials price standard of $2.00 per pound. 4600 pounds of materials were purchased at $2.20 a pound. The actual ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.