Whitmer Corporation is working on its direct labor budget for the next two months. Each unit of output requires 0.07 direct labor-hours. The direct labor rate is $9.00 per direct labor-hour. The production budget calls for producing 4,200 units in February and 4,700 units in March. Required: Prepare the direct labor budget for the next two months, assuming that the direct labor work force is fully adjusted to the total direct labor-hours needed each month. (Round "labor-hours per unit"

+1
Answers (1)
  1. 19 February, 09:29
    0
    Results are below.

    Explanation:

    Giving the following information:

    Each unit of output requires 0.07 direct labor-hours. The direct labor rate is $9.00 per direct labor-hour. The production budget calls for producing 4,200 units in February and 4,700 units in March.

    Direct labor budget of February:

    Direct labor hours = 4,200*0.07 = 294

    Direct labor cost = 294*9 = $2,646

    Direct labor budget of March:

    Direct labor hours = 4,700*0.07 = 329

    Direct labor cost = 329*9 = $2,961
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Whitmer Corporation is working on its direct labor budget for the next two months. Each unit of output requires 0.07 direct labor-hours. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.