Ask Question
12 July, 05:04

For a project, the following earned value data have been assessed: AC: $ 4,000,000 CV: $ - 500,000 SPI: 1.12 BAC: $ 9,650,000 What is the Planned Value (BCWS) of the project at the time of the assessment?

+1
Answers (1)
  1. 12 July, 08:37
    0
    The BCWS is also known as Planned Value (PV).

    So, in this way, PV = 3.125.000

    Explanation:

    With the data we can obtain the PV as follows:

    First, let's calculate EV as EV = CV + AC.

    EV = - 500.000 + 4.000.000 = 3.500.000

    After this, we can calculate PV with this formula: SPI = EV/PV

    PV = EV/SPI

    PV = 3.500.000/1.12 = 3.125.000

    We can conclude, with these results, that the project actually is forward about the schedule but with an overcost about the budget. In other words, the project advance must be 41% but now is on 36% due to the negative variance on the costs (CV).
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “For a project, the following earned value data have been assessed: AC: $ 4,000,000 CV: $ - 500,000 SPI: 1.12 BAC: $ 9,650,000 What is the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers