The constraint at Dalbey Corporation is time on a particular machine. The company makes three products that use this machine. Data concerning those products appear below: FE MB WPSelling price per unit $260.00 $365.80 $181.40Variable cost per unit $186.00 $269.88 $127.44Minutes on the constraint 5.20 7.00 4.00Assume that sufficient time is available on the constrained machine to satisfy demand for all but the least profitable product. Up to how much should the company be willing to pay to acquire more of this constrained resource? (Round your intermediate calculations and final answer to 2 decimal places.) (A) $14.23 per minute (B) $13.49 per minute (C) $53.96 per unit (D) $95.92 per unit

+2
Answers (1)
  1. 10 July, 08:35
    0
    Price Per Unit for FE = Selling price - Variable price = 260-186 = $74

    Price Per Unit for MB = 365.80-269.88 = $95.92

    Price Per Unit for WP = 181.40-127.44 = $53.96

    Price per Minute for FE = 74/5.20 = $14.23

    Price Per Minute for MB = 95.92/7 = $13.70

    Price Per Minute for WP = 53.96/4 = $13.49

    The least profitable unit per minute is WP ($13.49 per minute) or $53.96 per unit. So the answer is C
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The constraint at Dalbey Corporation is time on a particular machine. The company makes three products that use this machine. Data ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers