The standard cost card for one unit of a finished product shows the following: Standard Quantity or Hours Standard Price or Rate Direct materials 12 feet $? per foot Direct labor 1.5 hours $ 12 per hour Variable manufacturing overhead 1.5 hours $ 8 per hour If the total standard variable cost for one unit of finished product is $78, then the standard price per foot for direct materials is:

+2
Answers (1)
  1. 9 March, 01:57
    0
    Direct Material per foot = $4

    Explanation:

    total variable = Direct material + labor + variable overheard

    $78 = D. M + (1.5 hrs * $12) + (1.5 hrs * $8)

    $78 = D. M + $18 + $12

    $78 = D. M + $30

    D. M = $78 - $30

    D. M = $48

    D. M (per foot) = $48/12 = $4
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The standard cost card for one unit of a finished product shows the following: Standard Quantity or Hours Standard Price or Rate Direct ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers