the details of weekly output and imput for fabication process are follows: output is 400 units, with a standard selling price of $100 per unit. For the week, total labor costs are: 10 workers at 40 hours for the week, are paid $15 per hour. Total material costs for the 400 units are $5,000. Weekly overhead is charged at the rate of 1.5 times the labor costs. What is the multifactor productivity for the week?

+4
Answers (1)
  1. 30 September, 09:02
    0
    Multifactor productivity = 2

    Explanation:

    Given:

    Total output = 400 units

    Standard selling price = $100 per unit

    Labor costs = $15 per hour

    Number of workers = 10 workers

    Number of hour = 40 hours per week

    Total material costs = $5,000

    Overhead = 1.5 times of (Total labor cost)

    Calculation:

    Total output = 400 x $100 = $40,000

    Total labor cost = $15 x 10 x 40 = $6,000

    Overhead = Total labor cost x 1.5 = $6,000 x 1.5 = $9,000

    Multi factor productivity = Total output / (Total labor cost + Total material cost + Overhead)

    = $40,000 / ($6,000 + $5,000 + $9,000)

    = $40,000 / $20,000

    Multifactor productivity = 2
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “the details of weekly output and imput for fabication process are follows: output is 400 units, with a standard selling price of $100 per ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.