Ask Question
1 April, 00:16

Tile & Grout (T&G) contracts to resurface the insides of the pools at WaterWorld Park. T&G knows that without the resurfacing, WaterWorld will have to delay its seasonal opening. T&G does not perform as promised. As consequential damages, WaterWorld can recoverA) the cost of new poolsB) the difference between T&G's price and the eventual cost of resurfacing. C) the loss of profit from the delayed opening. D) nothing.

+1
Answers (1)
  1. 1 April, 03:20
    0
    The answer is Letter C

    Explanation:

    Water World can recover the loss of profit from the delayed opening.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Tile & Grout (T&G) contracts to resurface the insides of the pools at WaterWorld Park. T&G knows that without the resurfacing, WaterWorld ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers