Keegan Inc. budgeted? 10,500 pounds of direct materials costing? $18.00 per pound to make? 4,900 units of product. The company actually purchased? 10,600 pounds of direct materials costing? $27.50 per pound to make the? 4,900 units. What is the direct materials price? variance?

A.$99,750 unfavorable

B.$100,700 favorable

C.$100,700 unfavorable

D.$99,750 favorable

+2
Answers (1)
  1. 14 April, 02:46
    0
    C.$100,700 unfavorable

    Explanation:

    The computation of the material price variance is shown below:

    = Actual Quantity * (Standard Price - Actual Price)

    = 10,600 pounds * ($18 - $27.50)

    = 10,600 pounds * $9.5

    = $100,700 unfavorable

    Simply we take the difference between the standard and actual price and then multiplied it by the actual quantity so that the actual amount can come.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Keegan Inc. budgeted? 10,500 pounds of direct materials costing? $18.00 per pound to make? 4,900 units of product. The company actually ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.