Ask Question
20 December, 05:29

Marcus is asked by higher management to create a document that provides a high level description of a project that has not yet been approved. The document should describe the major deliverables of the project and should provide the financial and strategic justification for the project. In this scenario, Marcus needs to prepare a

+2
Answers (1)
  1. 20 December, 07:39
    0
    Project charter

    Explanation:

    Project charter is the formal document, which is usually a short document and define the project in its entirely, involving what the goals are, who are the stakeholders and how it will be carried out.

    It is a very crucial ingredient in planning the project as it is used through out the lifecycle of the project. The needs or the requirement of the project charter are mark the milestones that everyone agreed on the activities or deliverables which could be expected before the project end date.

    So, Marcus require to made or prepare the project charter, which describe the deliverables and also the strategic as well as financial justification for the project.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Marcus is asked by higher management to create a document that provides a high level description of a project that has not yet been ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers