MegaRock produces quick setting concrete mix. Production of 200,000 tons was started in April, 190,000 tons were completed. Material costs were $3,152,000 for the month while conversion costs were $591,000. There was no beginning work-in-process; the ending work-in-process was 70% complete. What is the cost of the product that was completed and transferred to finished goods?

a.) $3,610,000.

b.) $3,555,850.

c.) $2,994,400.

d.) $3,743,000.

+5
Answers (1)
  1. 29 September, 09:53
    0
    A. $3,610,000

    Explanation:

    The Equivalent production = 190,000 + [70% * (200,000 - 190,000) ] = 197,000 tons.

    While the Cost per unit = ($3,152,000 + $591,000) / 197,000 = $19;

    the transferred costs = 190,000 * $19 = $3,610,000

    = $3,610,000 which is the final answer.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “MegaRock produces quick setting concrete mix. Production of 200,000 tons was started in April, 190,000 tons were completed. Material costs ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.