A PERT network consists of activities linked by arrows. Suppose two of the activities on the network are labeled "A" and "B." An arrow from "A" to "B" indicates that

+1
Answers (1)
  1. 6 April, 16:20
    0
    Task A must be completed before you can start with task B.

    Explanation:

    A Program Evaluation Review Technique (PERT) network is a project management technique used to schedule, organize and coordinate tasks. It was first developed by the navy during the 1950s as a way to manage their submarine missile program.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A PERT network consists of activities linked by arrows. Suppose two of the activities on the network are labeled "A" and "B." An arrow from ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.