In their Portland, Oregon facility, Wavy Wood Works makes several types of wood bowls from coastal drift wood. To make a bowl, the first step is to clean the drift wood. Each piece of drift wood makes a single bowl. There is one cleaning machine. It takes 40 seconds to load each piece of wood and the machine can hold up to 35 pieces. Once all of the pieces are loaded into the machine, it takes 45 minutes to clean the set (no matter the number of pieces in the set). Once the wood is cleaned, 15 skilled artisans carve the bowls, each one takes on average 100 minutes to produce each bowl. After carving, bowls are finished with a stain. It takes 30 seconds to load each bowl into the stain machine. The staining machine holds up to 35 bowls. Once all of the bowls are loaded, they are soaked for 80 minutes. After staining, bowls are unloaded onto drying racks. There is plenty of space on the drying racks.

What is the maximum capacity (bowls per hour) of this process?

+5
Answers (1)
  1. 9 February, 02:48
    0
    What is the maximum capacity (bowls per hour) of this process? 9 bowls per hour

    Suppose Wavy wants to operate with the same number of bowls in each batch that is cleaned or stained. For example, if they clean in batches of 30, then they stain in batches of 30 as well. What batch size in bowls minimizes their inventory while allowing the process at the maximum flow rate? 28 bowls per batch
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “In their Portland, Oregon facility, Wavy Wood Works makes several types of wood bowls from coastal drift wood. To make a bowl, the first ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers