Ask Question
27 June, 05:24

Assume that activity G has the following times: Early start time 7 days Early finish time 13 days Late start time 15 days Late finish time - 21 days Which of the following statements is TRUE about activity G? a. Activity G takes 14 days to complete. b. Activity G has a slack time of 8 days. c. Activity G is on the critical path. d. Activity G takes 2 days to complete.

+1
Answers (1)
  1. 27 June, 07:40
    0
    The correct answer is Activity G has s slack time of 8 days.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Assume that activity G has the following times: Early start time 7 days Early finish time 13 days Late start time 15 days Late finish time ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers