Assume that activity G has the following times: Early start time 7 days Early finish time 13 days Late start time 15 days Late finish time - 21 days Which of the following statements is TRUE about activity G? a. Activity G takes 14 days to complete. b. Activity G has a slack time of 8 days. c. Activity G is on the critical path. d. Activity G takes 2 days to complete.
+1
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Assume that activity G has the following times: Early start time 7 days Early finish time 13 days Late start time 15 days Late finish time ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.