Toby Company has budgeted three hours of direct labor per recliner at a standard cost of $30 per hour. During January, 650 actual hours were worked, completing 200 recliners. All were sold and Toby Company's actually labor was $31 per hour. What is Toby Company's direct labor efficiency variance for January?
+5
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Toby Company has budgeted three hours of direct labor per recliner at a standard cost of $30 per hour. During January, 650 actual hours ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Home » Business » Toby Company has budgeted three hours of direct labor per recliner at a standard cost of $30 per hour. During January, 650 actual hours were worked, completing 200 recliners. All were sold and Toby Company's actually labor was $31 per hour.