Ask Question
30 July, 01:46

Which one of the following statements is false?

A. There may be more than one critical path in a project network.

B. The critical path is the sequence of activities between a project's start and finish that takes the shortest time to complete.

C. If one of the activities on the critical path is delayed, the entire project will be delayed.

D. The activities along the critical path determine the completion time of the project.

+4
Answers (1)
  1. 30 July, 01:54
    0
    B

    Explanation:

    B. The critical path is the sequence of activities between a project's start and finish that takes the shortest time to complete.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Which one of the following statements is false? A. There may be more than one critical path in a project network. B. The critical path is ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers