Ask Question
6 February, 23:37

During 2012, Pavers Manufacturing expected Job No. 59 to cost $300,000 of overhead,$500,000 of materials, and $200,000 in labor. Pavers applied overhead based on directlabor cost. Actual production required an overhead cost of $280,000, $550,000 inmaterials used, and $220,000 in labor. All of the goods were completed. How much isthe amount of over - or underapplied overhead?

+2
Answers (1)
  1. 7 February, 01:18
    0
    The amount of over applied overhead is $50,000

    Explanation:

    The computation is shown below:

    First, Calculate the predetermined overhead rate which equals to

    = (Overhead cost : labor cost) * 100

    = ($300,000 : $200,000) * 100

    = 150%

    So, the applied overhead equals to

    = 150% * actual labor cost

    = 150% * $220,000

    = $330,000

    So, the over/under applied overhead equals to

    = Applied overhead - actual overhead

    = $330,000 - $280,000

    = $50,000 over applied
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “During 2012, Pavers Manufacturing expected Job No. 59 to cost $300,000 of overhead,$500,000 of materials, and $200,000 in labor. Pavers ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers