All of the following are true regarding Plan Communications Management except for which one? A. The communications management plan is a component plan of the project management plan. B. This process should be completed as early in the project as possible. It is used to define and manage the flow of project information. C. It's tightly linked with enterprise environmental factors, and all organizational process assets are used as inputs for this process. D. Data gathering, communication technology, communication methods, and expert judgment are some of the tools and techniques of this process.

+2
Answers (1)
  1. 19 December, 14:07
    0
    D. Data gathering, communication technology, communication methods, and expert judgment are some of the tools and techniques of this process.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “All of the following are true regarding Plan Communications Management except for which one? A. The communications management plan is a ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers