You can either invest in Project A or B. Project A could have a value of $150 with a probability of 0.1 or a value of $75 with a probability of 0.9. Project B could have a value of $110 with a probability of 0.2 or a value of $65 with a probability of 0.8. Which project should you invest in

+2
Answers (1)
  1. 15 February, 22:06
    0
    I will invest in Project A, as its Expected value is higher than the project B.

    Explanation:

    Project A

    Return Probability Expected Value

    $150 0.1 $150 x 0.1 = $15

    $75 0.9 $75 x 0.9 = $67.5

    Total Expected Value = $15 + $67.5 = $82.5

    Project B

    Return Probability Expected Value

    $110 0.2 $110 x 0.2 = $22

    $65 0.8 $65 x 0.8 = $52

    Total Expected Value = $22 + $52 = $74

    The Expected return of Project A is higher, I will invest in the Project A.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “You can either invest in Project A or B. Project A could have a value of $150 with a probability of 0.1 or a value of $75 with a ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.