Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below:HoursWait time 12.7Process time 1.8Inspection time 0.2Move time 4.4Queue time 6.1The delivery cycle time was:

+2
Answers (1)
  1. 22 May, 19:18
    0
    The delivery cycle time was 25.2 hours

    Explanation:

    Working notes:

    Consider the following formula to solve the exercise

    delivery cycle time=Wait time+Process time+Inspection time+Move time+Queue time

    = (12.7+1.8+0.2+4.4+6.1)

    which is equal to = 25.2 hours.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below:HoursWait time ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.