Ask Question
Today, 18:36

The Market Outlet has a beta of 1.38 and a cost of equity of 14.945 percent. The risk-free rate of return is 4.25 percent. What discount rate should the firm assign to a new project that has a beta of 1.25?

+3
Answers (1)
  1. Today, 20:08
    0
    The discount rate assign to a new project with a Beta of 1.25 is 13.94%

    Explanation:

    The applicable formula is the Capital Asset Pricing Model formula of Miller and Modgliani quoted below:

    Ke = Rf + (Market risk premium x Beta)

    Currently Ke=14.945%

    Beta = 1.38

    Risk free rate of return (Rf) is 4.25%

    Market risk premium is the unknown

    14.945%=4.25% + (Market Risk Premium) * 1.38

    14.945%-4.25%=Market Risk Premium*1.38

    10.70% = Market Risk Premium*1.38

    10.70%/1.38=Market Risk Premium

    Market Risk Premium = 7.75%

    However, the new project cost of equity has to be determined due to having a different Beta factor of 1.25 (a different risk appetite)

    Using the above formula, we have

    Ke=4.25% + (7.75% * 1.25)

    Ke = 13.94%
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The Market Outlet has a beta of 1.38 and a cost of equity of 14.945 percent. The risk-free rate of return is 4.25 percent. What discount ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.