Wright Corporation had the following information available for December of the current year:Work in process, December 1 $20,000 Materials placed into production, December 27,500 Direct labor, December 37,500 Plantwide overhead rate is 150% of direct labor costs. Job cost sheets had the following balances: Job Z1 $32,500 Job Z2 55,000 Job Z3 35,000 Job Z4 18,750 Jobs Z3 and Z4 were not completed at the end of December. What is the balance in work-in process for Wright at the end of December? Select one:

a. $85,000

b. $87,500

c. $56,250

d. $53,750

+3
Answers (2)
  1. 4 January, 20:29
    0
    d. $53,750

    Explanation:

    Balance in work-in process = Cost of Job Z3 + Cot of Job Z4

    = 35000 + 18750

    = $53,750

    Therefore, The balance in work-in process for Wright at the end of December is $53,750.
  2. 4 January, 20:59
    0
    The answer is d. $53,750
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Wright Corporation had the following information available for December of the current year:Work in process, December 1 $20,000 Materials ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers