A firm has 56 units of product X on hand. Forecasts of demand are for 20 units per week. An MPS quantity of 100 units is planned to arrive in period 3. Customer orders are 24 for period 1, 18 for period 2, and 15 for period 3. What quantity is available for commitment to new customers prior to the receipt of the MPS quantity in week 3

+5
Answers (1)
  1. 19 May, 15:44
    0
    Answer: 14
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A firm has 56 units of product X on hand. Forecasts of demand are for 20 units per week. An MPS quantity of 100 units is planned to arrive ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.