Ask Question
29 July, 16:54

Which two steps of project team building are out of sequence?

A) You always identify skills before you identify people.

B) You always negotiate with the functional supervisor before you negotiate with top management.

C) You always negotiate with the functional supervisor before you talk to potential team members.

D) You always identify personnel before you talk to potential team members.

+5
Answers (1)
  1. 29 July, 20:46
    0
    A and D are out of sequence.

    Explanation:

    in A) You first need to identify people in order to know who posses what skill and who is best at what.

    in D) before having any personnel for any position there must be a meeting with potential team members and not everyone who is a potential team member will be a member of the team.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Which two steps of project team building are out of sequence? A) You always identify skills before you identify people. B) You always ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers