Edison Corporation's variable manufacturing overhead rate is $5.00 per direct labor-hour. Total budgeted fixed overhead is $25,000 per month. The $25,000 per month includes $7,000 in depreciation expense. Total budgeted direct labor-hours for the month of July is 20,000. Based on the month of July only, the predetermined overhead rate is $. Total budgeted manufacturing overhead for July is: ___.

+2
Answers (1)
  1. 24 April, 12:58
    0
    Manufacturing overhead for July will be $55000

    Explanation:

    We have given budgeted labor hour in month of July = 20000

    Variable overhead rate = $5

    So variable manufacturing overhead = 20000*$5 = $100000

    Fixed manufacturing overhead = $25000

    Now total manufacturing overhead = $100000+$25000 = $125000

    Depreciation expense = $7000

    So manufacturing overhead for July = $125000 - $7000 = $55000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Edison Corporation's variable manufacturing overhead rate is $5.00 per direct labor-hour. Total budgeted fixed overhead is $25,000 per ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.