The phases of project management are: A. planning, scheduling, and controlling. B. planning, programming, and budgeting. C. planning, organizing, staffing, leading, and controlling. D. different for manufacturing projects than for service projects. E. GANTT, CPM, and PERT.

+4
Answers (1)
  1. 30 March, 14:35
    0
    A. planning, scheduling, and controlling.

    Explanation:

    The phases of project management are -

    1. Initiation

    2. Planning

    3. Execution - Scheduling

    4. Control

    5. Close

    Option A is correct because the answer includes the 2nd, 3rd, and fourth phases of project management.

    Option B is wrong because programming is not a phase of project management. Option C is a combination of management functions. Therefore, it is incorrect. Option D is not correct as the service project is not different from the manufacturing project. Option E is the project management technique.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “The phases of project management are: A. planning, scheduling, and controlling. B. planning, programming, and budgeting. C. planning, ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers