Johnson Construction Company uses cost-plus pricing to determine costs and place bids on local jobs. The manager needs to compute the cost-plus price to place a bid on a custom room addition job. The estimated cost associated with the new room addition is $500,000. The markup on the project cost is 35%. What is the cost-plus price required to bid on the new custom room addition job?

+3
Answers (1)
  1. 6 February, 23:32
    0
    What is the cost-plus price required to bid on the new custom room addition job?

    $675000

    Explanation:

    Cost plus pricing=break even price*profit marginal goal

    Cost plus pricing=500000*1,35

    Cost Plus pricing=675000
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “Johnson Construction Company uses cost-plus pricing to determine costs and place bids on local jobs. The manager needs to compute the ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.
Search for Other Answers