ABC Manufacturing uses a Kanban system for a component. The daily demand is 800 units. Each container has a combined waiting and processing time of 0.34 days. If the container size is 50 and efficiency (safety) factor is 9 percent, how many Kanban card sets should be authorized (round up) ?
+4
Answers (1)
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “ABC Manufacturing uses a Kanban system for a component. The daily demand is 800 units. Each container has a combined waiting and processing ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.