James received a report from the production and purchasing departments with the following values for January: Actual materials quantity: 90,000 pounds Total actual cost: $47,200 Standard materials quantity: 5.5 pounds/unit Standard price: $0.55/pound Units made: 16,300 Two days later, he got a correction report from the purchasing department that they found another invoice for $6,200. How much would James' materials price variance change for the month of January?

A : $3,900 F

B : $3,900 U

C : $6,200 U

D : $6,200 F

+1
Answers (1)
  1. 13 December, 17:27
    0
    The correct answer is B.

    Explanation:

    Giving the following information:

    Actual materials quantity: 90,000 pounds

    Total actual cost: $47,200 + 6,200 = $53,400

    Standard materials quantity: 5.5 pounds/unit

    Standard price: $0.55/pound

    Units made: 16,300

    We need to use the following formula:

    Direct material price variance = (standard price - actual price) * actual quantity

    Direct material price variance = (0.55 + 53,400/90,000) * 90,000 = $3,900 unfavorable
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “James received a report from the production and purchasing departments with the following values for January: Actual materials quantity: ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.