A toll tunnel has decided to experiment with the use of a debit card for the collection of tolls. Initially, only one lane will be used. Cars are estimated to arrive at this experimental lane at the rate of 750 per hour. It will take exactly four seconds to verify the debit card.

In how much time would you expect the customer to wait in line, pay with the debit card, and leave?

How many cars would you expect to see in the system?

+2
Answers (1)
  1. 21 October, 01:26
    0
    Solution:

    a. λ = 750

    u = 1 card/4sec = 900 cards / hour

    L (q) = 750^2 / 2*900 (900-750) = 2.0833

    L (s) = 2.0833+750/900 = 2.9166 W (s)

    = 2.9166 / 750 = 0.003889

    = 14.00 sec

    In 14.00 sec would you expect the customer to wait in line, pay with the debit card, and leave

    b. L (s) 2.9166 = 3 cars (from the answer of question a)

    3 cars would expect to see in the system.
Know the Answer?
Not Sure About the Answer?
Find an answer to your question ✅ “A toll tunnel has decided to experiment with the use of a debit card for the collection of tolls. Initially, only one lane will be used. ...” in 📘 Business if you're in doubt about the correctness of the answers or there's no answer, then try to use the smart search and find answers to the similar questions.